Cheniere Energy, Inc. (“Cheniere” or the “Company”) (NYSE: LNG) today announced that liquefied natural gas (“LNG”) was produced for the first time from the first train (“Train 1”) of the Company’s Corpus Christi Stage 3 Liquefaction Project (“CCL Stage 3”). The commissioning process continues, and Cheniere expects substantial completion of Train 1 to be achieved at the end of the first quarter of 2025, over six months ahead of the guaranteed completion date. Upon substantial completion, Bechtel Energy, Inc. (“Bechtel”) will transfer care, custody and control of the completed train to Cheniere.
Full notice to proceed on CCL Stage 3 was issued to Bechtel by Cheniere in June 2022. CCL Stage 3 consists of seven midscale trains, with an expected total production capacity of over 10 million tonnes per annum (“mtpa”) of LNG. As of November 30, 2024, overall project completion for CCL Stage 3 was 75.9%, which reflects engineering 96.8% complete, procurement 97.2% complete, subcontract work 87.7% complete and construction 39.2% complete. Upon substantial completion of all seven trains of CCL Stage 3, the expected total production capacity of the Corpus Christi liquefaction facility will be over 25 mtpa of LNG.
Subscribe to:
Post Comments (Atom)
XRG Agrees to Acquire Interest in Australia's North West Shelf Project
XRG today announced it has entered into an agreement to acquire Shell's interest in the North West Shelf project in Western Australia, ...
-
Glenfarne Group’s Texas LNG project has signed a definitive 20-year Sales and Purchase Agreement with Macquarie Energy LLC, a subsidiary of...
-
A cool down cargo of liquefied natural gas (LNG) from Ras Laffan, Qatar has berthed at the Golden Pass LNG terminal in Sabine Pass, Texas – ...
-
Argent LNG LCC (Argent LNG) has selected Baker Hughes (NASDAQ: BKR), an energy technology company, as the liquefaction solution and related...
No comments:
Post a Comment